January | 11, 1915, | Engineers presented final detailed plans and specifications. |
January | 11, 1915, | Commission adopted plans and specifica— tions and ordered work advertised. |
February | 23, 1915, | Commission received bids for all principal construction work. |
February | 27, 1915, | Commission awarded contracts for principal construction work. |
March | 6, 1915, | Actual construction formally started. |
Engineers presented and Commission adopted plans and specifications for Derby Street approach embankment. Commission received bids for Derby Street approach embankment. Commission awarded contract Derby Street approach embankment. Final approval of plans given by Secretary of War. Engineers presented and Commission adopted plans and specifications for pavement of approach embankments. Commission received bids for pavement of approach embankments. Commission awarded contract for pavement of approach embankments. Commission awarded contract making purchase of materials for lighting system. Commission awarded contract for constructing lighting system. Bridge formally opened to trailic. Engineers rendered final estimate for last contract. |