This page has been proofread, but needs to be validated.
18c. 54
Sale of Goods Act 1979

Part VI

(2) Where, under a contract of sale, the price is payable on a day certain irrespective of delivery and the buyer wrongfully neglects or refuses to pay such price, the seller may maintain an action for the price, although the property in the goods has not passed and the goods have not been appropriated to the contract.

(3) Nothing in this section prejudices the right of the seller in Scotland to recover interest on the price from the date of tender of the goods, or from the date on which the price was payable, as the case may be.

Damages for non-acceptance. 50.—(1) Where the buyer wrongfully neglects or refuses to accept and pay for the goods, the seller may maintain an action against him for damages for non-acceptance.

(2) The measure of damages is the estimated loss directly and naturally resulting, in the ordinary course of events, from the buyer’s breach of contract.

(3) Where there is an available market for the goods in question the measure of damages is prima facie to be ascertained by the difference between the contract price and the market or current price at the time or times when the goods ought to have been accepted or (if no time was fixed for acceptance) at the time of the refusal to accept.

Buyer’s remedies

Damages for non-delivery. 51.—(1) Where the seller wrongfully neglects or refuses to deliver the goods to the buyer, the buyer may maintain an action against the seller for damages for non-delivery.

(2) The measure of damages is the estimated loss directly and naturally resulting, in the ordinary course of events, from the seller’s breach of contract.

(3) Where there is an available market for the goods in question the measure of damages is prima facie to be ascertained by the difference between the contract price and the market or current price of the goods at the time or times when they ought to have been delivered or (if no time was fixed) at the time of the refusal to deliver.

Specific performance. 52.—(1) In any action for breach of contract to deliver specific or ascertained goods the court may, if it thinks fit, on the plaintiff’s application, by its judgment or decree direct that the contract shall be performed specifically, without giving the defendant the option of retaining the goods on payment of damages.

(2) The plaintiff’s application may be made at any time before judgment or decree.