The Severn Tunnel
Appearance
THE
SEVERN TUNNEL:
Its Construction and Difficulties.
1872-1887.
BY
THOMAS A. WALKER.
WITH FIVE PORTRAITS ON STEEL AND UPWARDS OF FORTY SKETCHES AND PLANS.
LONDON:
RICHARD BENTLEY & SON, NEW BURLINGTON STREET.
Publishers in Ordinary to Her Majesty the Queen.
1888.
Sir John Hawkshaw, F.R.S. |
Engraved by G. J. Stodart from a photograph by Barraud |
DEDICATION.
The following account of some of the difficulties met with in the construction of the Severn Tunnel, and how they were surmounted, is, by kind permission, dedicated to the Engineer-in-Chief, Sir John Hawkshaw, of whose professional skill and indomitable perseverance the Tunnel itself will ever remain a lasting monument.
T. A. W.
June 14, 1888.
Thomas A. Walker |
Engraved by G. J. Stodard from a photograph by Barbaud |
London, Richard Bentley and Son, 1888 |
Preface | vi | |
List of Portraits on Steel | xi | |
List of Illustrations | xiii | |
I. | Description of the estuary of the Severn, and the country in the immediate neighbourhood of the Severn Tunnel. | 1 |
II. | The early history of the undertaking. | 11 |
III. | The commencement of the works under the contract. | 26 |
IV. | The final struggle. | 45 |
V. | Great snow storm; strike among the miners; River Severn breaks in on the sea-wall side. | 59 |
VI. | Tunnelling. | 77 |
VII. | A year of good progress [1882]. | 98 |
VIII. | Further progress and greater troubles. | 119 |
IX. | A week of troubles. | 127 |
X. | The means taken to deal with the great spring. | 137 |
XI. | Side-heading drvien to Big Spring; completion of the Brickwork; Big Spring shut out; works passed by Board of Trade. | 144 |
XII. | The men by whom the work was done. | 165 |
Appendix: Description of the large pumps by Messrs. Harvey, of Hayle Foundry. | 180 |
LIST OF PORTRAITS ON STEEL.
Sir John Hawkshaw, F.R.S. | frontispiece |
(engraved by J. G. Stodart) | |
Mr. Thomas A. Walker | to face preface |
(engraved by J. G. Stodart) | |
Mr. Charles Richardson | to face page 12 |
(engraved by W. H. Gibbs) | |
Mr. J. Clarke Hawkshaw | 157 |
(engraved by W. H. Gibbs) | |
Mr. Harrison Hayter | 166 |
(engraved by W. H. Gibbs) |
LIST OF ILLUSTRATIONS.
TO FACE PAGE | |
View of Telford’s Bridge at Gloucester | 1 |
„„The Severn (Railway) Bridge | 2 |
„„Sudbrook Chapel | 4 |
Map (1-inch Ordnance) showing Line of the Severn Tunnel | 10 |
Plan of Sudbrook in 1873 (before the Severn Tunnel was commenced) | 14 |
Plan showing Position of the Old Shaft, Iron Shaft, and Headings | 16 |
Section showing all Headings driven when the ‘Big Spring’ broke in | 18 |
Plan of Sudbrook in 1879 | 18 |
Plan of Shield put in the Old Shaft to keep back the ‘Big Spring’ | 28 |
Longitudinal Section of the Severn Tunnel, showing Geological Strata as found | 32 |
Cross Section of Tunnel, showing Arch | 34 |
Plan of Sudbrook in 1880 | 38 |
Plan of Headwalls and Doors in the Heading at Sudbrook | 54 |
View of Portskewett Pier, with the Tunnel Works in the distance | 66 |
Plan of Methods of Timbering Headings | 80 |
„„‘Breaking up’ from the Heading | 82 |
„„Break-up Length with Centres | 84 |
„„Timbering for Tunnel in Soft Ground | 86 |
Section showing Method of Sinking 29-foot Shaft and Curbs | 88 |
View of Sir John Hawkshaw inspecting the Works, and at Work in the Tunnel | 102 |
Plan of the Infirmary at Sudbrook | 106 |
„„the New Mission Hall, Sudbrook | 108 |
View of Sudbrook | 118 |
Plan of Sudbrook in 1882 | 118 |
„„Cavity, Headwall, and all Headings near the ‘Big Spring’ | 124 |
View of the Temporary Engine-Houses at Sudbrook | 130 |
„„the Permanent Engine-Houses at Sudbrook | 130 |
„„Men in Boat sawing the Timber | 132 |
„„Flooded Cutting | 134 |
Plan of the Temporary Pumping-Engines for the Great Spring and Pumps in the Tunnel | 138 |
Elevation of Temporary Engine-Houses for the Great Spring | 140 |
View of the Fever Hospital at Sudbrook | 142 |
Plan of the Fever Hospital at Sudbrook | 142 |
„„Side-Heading to the Great Spring | 146 |
„„Fissure and all Headings at Great Spring | 148 |
„„Sudbrook in 1884 | 150 |
Progress Sections for the Years 1881-4 | 151 |
Plan of Permanent Pumps at Sudbrook—Engines and Pumps at top of Shaft | 164 |
Plan of Permanent Pumps—Plan of Engines round Shaft | 164 |
Plan of Permanent Pumps—Pumps in Shaft | 164 |